 I click on the Resource Sheet view and notice that one of the resource names appears in Red.  What does this mean?

Comment viewing options

Select your preferred way to display the comments and click "Save settings" to activate your changes.

#

It means the resource is over allocated. When you open the resource sheet and see that there is a red appears on one of the resource names, it means that the resource is over allocated.

Your resource sheet will display each resource in a number of tables.

It is very useful if your creating a project resource pool, especially if your using some tables on your entry,or if your using the entry table as its fields are most appropriate to your resource definition process. Resource sheet on making a project you should be able to use table as an entry for your fields.